REFURBISHMENT AND DEMOLITION ASBESTOS SURVEY · ESSEX AND LONDON
A refurbishment and demolition asbestos survey locates asbestos in the part of a building about to be worked on, before the work starts. It is intrusive by design: floors, ceilings and wall linings are opened up within the work area so nothing is left to be found by a contractor mid-job. Regulation 5 of the Control of Asbestos Regulations 2012 requires asbestos to be identified before refurbishment or demolition, and HSE guidance HSG264 sets out how. Based in Great Wakering near Southend-on-Sea, we cover Essex, London and the wider South East.
Floors lifted, ceilings dropped and linings opened where the works reach, so what is behind them is recorded before a contractor meets it.
We survey the area the works actually touch, set against your drawings and scope, and say plainly where the survey boundary stops.
Sampling strategy, caveats, plans and photographs follow HSG264, in a format a principal contractor and demolition team can work from.
Openings are sealed and the area left safe, with a record of every opening made, so the building can stay in use until the works begin.
What It Covers
A management survey looks at what people could disturb in ordinary use. This survey assumes the opposite: that somebody is about to take the building apart. So the surveyor goes where a contractor will go. Suspended ceilings come down, floor coverings come up, boxing is opened, risers and ducts are entered, and linings are cut into where the drawings show work. Every opening is recorded and made good, and the report states exactly which areas were accessed and which were not.
Scope is set against your drawings and the works you have planned, not against the whole building. A strip-out of two floors does not need the roof void surveyed; a full demolition does. Where the works are phased, the survey can be phased with them. What the report will never do is bless an area it did not open: anything not accessed is recorded as a caveat, and a contractor planning to work there needs it surveyed first. For a building staying in use, the survey you need is the asbestos management survey.
When It Applies
The duty sits with whoever commissions the work, which in practice means one of these four.
Landlords, tenants and fit-out contractors, before soft strip begins. The survey has to be done early enough to price any removal into the programme.
Full demolition means the whole structure is surveyed, including areas nobody has entered for years: ducts, voids, plant rooms and sub-floors.
CDM duties mean the pre-construction information has to tell every contractor on site what is present before any of them start work on site.
Taking out an Artex ceiling, lifting floor tiles or stripping a garage roof is still disturbance, and most builders will ask what is there first.
On the Day
The building is normally empty, or the work area is closed off. The surveyor works through the scope with hand tools, opening up where the drawings say work will reach, and keeping dust down while doing it: openings are small, controlled and sealed afterwards. Samples are bagged, labelled and logged against their location, and photographs are taken of every opening so the report shows what was behind each one.
Access is what decides the length of the visit. Power and lighting on, the area cleared of stock and furniture, keys for every room in scope, and drawings that match the building all shorten it. Where something cannot be opened safely on the day, whether live services, structural risk or a locked area nobody has keys for, it goes in the report as a caveat and we quote for a return visit rather than guessing. Samples go to an independent UKAS-accredited laboratory, and the report follows once the results are back.
Where We Look
Tiles come out and the grid is checked above: pipe runs, lining boards, soffit panels and the sprayed coatings sometimes found on steelwork behind them.
Coverings are lifted and the screed exposed, because thermoplastic tiles and the black bitumen adhesive under them survive long after the carpet above has been replaced.
Boxing is opened and risers entered. Vertical services are where lagging, rope seals and old board linings hide, and they are rarely touched between refurbishments.
Boilers, calorifiers, flues and their pipework, plus gaskets and panels inside the plant itself. Plant rooms carry the highest-risk materials in most buildings.
Roof sheets, cladding panels, gutters, soffits and flashings, including the tanks and flues in the roof void that a demolition crew will reach early.
Partition cores, infill panels and linings behind plasterboard, which is where insulating board turns up in buildings refurbished during the 1970s and 1980s.
Every opening we make is photographed, recorded and sealed, and anything outside the agreed scope is listed as a caveat rather than assumed to be clear.
What Follows
Three things usually happen between the report landing and the site being handed to the trades.
Non-licensed work by our own team; licensed work booked and managed by us and carried out by a licensed contractor, sequenced to your programme.
After licensed removal, four-stage clearance to less than 0.01 fibres per cubic centimetre, with the certificate of reoccupation that lets the works restart again.
Work stops, the area is isolated, and we attend to identify the material and set out what has to happen before the site can reopen and the work can resume safely.
The Legal Duty
Regulation 5 of the Control of Asbestos Regulations 2012 requires that, before any work that could disturb the fabric of a building, suitable and sufficient steps are taken to identify what materials are present and what condition they are in. The duty falls on whoever commissions and carries out the work, not only on whoever owns the building, which is why principal contractors and developers ask for the survey as part of the pre-construction information.
Approved Code of Practice L143 and HSE guidance HSG264 set out how the survey is planned, how intrusive it has to be and how it is reported. The alternative the regulations allow, presuming asbestos is present and working on that basis, is lawful but means treating every material as asbestos for the whole job, which costs more than the survey. The duty-to-manage side is covered on our duty to manage asbestos page, and the survey types are compared on the asbestos surveys hub.
Areas We Cover
Based in Great Wakering near Southend-on-Sea, we cover Essex, London and the wider South East.
We survey strip-outs, refurbishments and demolitions across Southend-on-Sea, Rochford, Rayleigh, Basildon, Chelmsford, Brentwood, Colchester and into East London, for developers, main contractors, landlords and homeowners. Because the survey, the sampling, the removal and the clearance come from one team, the programme does not stall between suppliers. See our accreditations for the pre-qualification paperwork.
Get in Touch
Tell us the building, the works planned and the programme dates, and send any drawings or scope you hold. We will come back with a fixed price, the time we need on site and the report turnaround. If asbestos may have just been disturbed on site, call 01702 690 693 rather than waiting for a reply. The contact page and our FAQ cover everything else.
Ora Asbestos Management Ltd
Unit 6, Crouchmans Yard, Poynters Lane,
Great Wakering, Essex, SS3 9TS
Hours: Monday–Saturday, 6am–6pm · Closed Sunday
Before the work starts, and early enough for any removal to be priced and programmed. Regulation 5 of CAR 2012 requires asbestos to be identified before refurbishment or demolition, so a survey booked the week work begins usually costs more in delay than it saves.
The work area does. The survey is intrusive, so the area in scope should be cleared of people, stock and furniture, with power and lighting available. The rest of the building can normally carry on as usual.
It opens it up where the works will reach. Ceilings are dropped, floor finishes lifted and linings cut into within the scope, then made good and sealed. Those areas are about to be stripped out anyway, so the damage is to parts of the building already coming out.
Yes, and that is normal. Scope is set against your drawings and works. The report states exactly which areas were in scope and which were not, and anything outside it has to be surveyed before work extends there.
It is recorded as a caveat rather than assumed to be clear. Live services, structural risk or a room nobody can open are the usual reasons. We quote for a return visit once access can be arranged.
No. A management survey is non-intrusive and covers a building in use, so it does not discharge Regulation 5. Starting works on the strength of one is a common and expensive mistake.
The report identifies it, says what it is and where, and whether removal is licensed or non-licensed work. We carry out non-licensed removal and arrange licensed work, with four-stage clearance before the area is handed back.
Yes. Surveys are phased with the works where that suits, and the report turnaround is agreed before we start, so removal can be priced and booked without holding up the following trades.
Cookies on this site
We use strictly necessary cookies to make this site work. With your permission we would also like to use analytics cookies to see how the site is used so we can improve it. You can change your choice at any time. See our cookie policy.